Updated the PAL, Communication log Project Portfolio and blogs to reflect the most recent project activities.
Met with the Network Engineering group to review their equipment count and rack design for the telecomm closet.
A facilities follow-up meeting with and the architects to discuss the 8 way duct bank and IT infrastructure for BE.
Working with client and Intech on client data storage requirements and design.
A site visit to the client to discuss their data storage requirements.
A facilities follow-up meeting with and the architects to discuss the 8 way duct bank and IT infrastructure for BE.
Follow up with the client and IT to discuss their data storage options.
Setup meeting with AV team lead and ITOC manager to review storage options for client.
Setup meeting to review vendor IT drawings.
Setup future meetings for IT progress meetings.