Updated the PAL, Communication log Project Portfolio and modify the blogs front page. The options for connectivity will be discussed with client and facilities.
Completed 70% construction drawing comments.
Following up with media resources on the estimate for large conference room.
Phase one needs to be completed first before building construction can start.
A GT BE Vault on site review took place on Oct 8th discussing Neman boxes and ABF tube type.
Two additional computer labs have been added to the project.
Client meetings with facilities to review furniture for labs.
Received AV design for large conference room.
Request for video conferencing in one of the break out rooms.
Follow up with media resource group on the AV sign off on large conference room design from client.
Following up with the college NE group on the estimated quote for IT equipment in the greenhouse.
Confirm ABF tube size for GT vaults with the college NE’s.