Updated the PAL, Communication log Project Portfolio and modify the blogs front page. The options for connectivity will be discussed with client and facilities.
Completed 70% construction drawing and specification comments.
Following up with media resources on the estimate for large conference room.
Phase one needs to be completed first before building construction can start.
The college NE group has decided to use 7 tube ABF as opposed to a 19 tube ABF. This will allow for a smaller nema box and provide an easier turn radius for the ABF.
The AV conference room has been approved and agreed by campus administrators.