Reviewing 50% CD and preparing comments on design.
Meet with AV, facilities, engineers, and ITV to confirm and review floor boxes, cabling of SIWS, number of conduits for the locations. Did a walkthrough of the Commons Building and Cultural Art Center that illustrated what and what not to do for ITV and AV standards.
Met with facilities, ITV, AV, architects, and engineers to discuss the large conference room design. A meeting was held on January 6th, 2010 that involved the college administration to discuss the conference room floor plan. It was decided that the conference room will be capable of splitting in half rather than quarters. Due to the change in design a meeting will be scheduled with the client to review a new design with the college AV and ITV groups.
A meeting was schedule for Jan 20th, 2010 with the NE and cabling to groups to review the amount of fiber required for the infrastructure connectivity in the building and out of the building.