Thursday, May 13, 2010

Progress Update

Updated the PAL, Communication log Project Portfolio and blogs to reflect the most recent project activities.

Reviewed the vendor telecommunication drawings with FIP group.

A facilities meeting on May 4th to discuss the duct bank path for data, voice, CATV, and electric. An eight way duct bank from SA to BE was agreed to during the meeting.

Setup future biweekly progress meetings through 2011.

Continue working with client and Intech on client data storage requirements and design.

Completed comments for Convergent Technology TA drawings and sent comments back to facilities.

A follow up with the Network Engineering group is setup for May 14th to discuss the data storage options in the ITOC.

Meeting setup with ITOC mangers to review and discuss the clients request for data space for students and faculty.

Follow up with ITV on their cable locations for the large conference room.
Setup meeting to review vendor IT drawings.