Thursday, June 10, 2010

Progress Update

Updated the PAL, Communication log Project Portfolio and blogs to reflect the most recent project activities.
Working with the ITV group on their cabling locations for the large conference room.
Complete Convergent Technology drawings comments and forward to facilities.
Review client storage request with network services. SharePoint was mentioned as a possible option.
Review Convergent Technology drawings comments with facilities.
Informed ITV about the meeting on the large conference room so they could have someone present at the meeting.
Reviewed the updated AV design drawings to reflect changes from the last set of drawings.
There was a meeting held on June 3rd with ITV, GT campus provost, media resources, and GT VP to discuss their vision of the design for the large conference room.
A meeting has been setup for June 17th to review the new updated AV construction drawings with facilities, vendor, and media resource group. This meeting is to clarify in concerns and design misunderstanding about the AV construction drawings.
Meeting is planned to be setup with the client for their IT requirements for the Greenhouse.

Thursday, June 3, 2010

Progress Update

Working with the ITV group on their cabling locations for the large conference room.
Complete Convergent Technology drawings comments and forward to facilities.
Review client storage request with network services. SharePoint was mentioned as a possible option.
Review Convergent Technology drawings comments with facilities.
Informed ITV about the meeting on the large conference room so they could have someone present at the meeting.
A meeting has been setup on June 4th to review and discuss the BE Large Conference with client and facilities.
Follow up with facilities on the 90% construction drawings.
Work with ITV to confirm their I/O panel sizes and type.