The 95% Construction drawings have updated the Access Point locations and estimated radius. This has been forward to facilities.
A meeting is scheduled for Dec 14th with facilities and IT contractor on floor box design and conduit paths for some AV devices.
Wednesday, December 14, 2011
Monday, November 21, 2011
Progress Update
Meet with IT vendor for facilities to review 95% comments.
Facilities working to prepare bid package
Follow up with media resource group on the meeting with the GT provost on the large conference room design.
Facilities working to prepare bid package
Follow up with media resource group on the meeting with the GT provost on the large conference room design.
Thursday, October 13, 2011
Progress Update
Completed FIP view of 95% Construction drawings.
BE 95% CD Review Meetings with facilities, engineers, and architects.
Facilities working to prepare bid package
URL Blog http://gtbioscienceprogressreport.blogspot.com/
Next two weeks
Germantown Bioscience building
Reschedule ITV meeting for late in November
Follow up with media resource group on the meeting with the GT provost on the large conference room design.
BE 95% CD Review Meetings with facilities, engineers, and architects.
Facilities working to prepare bid package
URL Blog http://gtbioscienceprogressreport.blogspot.com/
Next two weeks
Germantown Bioscience building
Reschedule ITV meeting for late in November
Follow up with media resource group on the meeting with the GT provost on the large conference room design.
Tuesday, October 4, 2011
Progress Update
Sent the CD 95% comments to facilities for review
Scheduled FIP review of 95% CD for September28th.
Next two weeks
Germantown Bioscience building
Meeting scheduled for Oct 4th. with the ITV group
BE: 95% CD Peer Review & Commissioning Session meeting set up for Oct 5th.
Follow up with media resource group on the meeting with the GT provost on the large conference room design.
Facilities scheduled Oct.5th meeting for 95% CD Peer Review & Commissioning Session
Site visit to HT with vendor for point to point communication to greenhouse.
Scheduled FIP review of 95% CD for September28th.
Next two weeks
Germantown Bioscience building
Meeting scheduled for Oct 4th. with the ITV group
BE: 95% CD Peer Review & Commissioning Session meeting set up for Oct 5th.
Follow up with media resource group on the meeting with the GT provost on the large conference room design.
Facilities scheduled Oct.5th meeting for 95% CD Peer Review & Commissioning Session
Site visit to HT with vendor for point to point communication to greenhouse.
Thursday, September 1, 2011
The project is in 95% CD phase.
The comments have been completed but not sent as of today.
•The FIP group needs to review all drawings prior to sending 95% CD comments a meeting has been schedule for later in September.
The bid is suppose to go on the street around November 2011.
All IT groups have been met with except ITV. The large conference room still has a question about the number of large screens to used Tow or four. Media Resources is planning to setup a meeting with the provost to review what GT request would be.
Meet with the ITV group
Follow up with media resource group on the meeting with the GT provost on the large conference room design.
The comments have been completed but not sent as of today.
•The FIP group needs to review all drawings prior to sending 95% CD comments a meeting has been schedule for later in September.
The bid is suppose to go on the street around November 2011.
All IT groups have been met with except ITV. The large conference room still has a question about the number of large screens to used Tow or four. Media Resources is planning to setup a meeting with the provost to review what GT request would be.
Meet with the ITV group
Follow up with media resource group on the meeting with the GT provost on the large conference room design.
Friday, August 5, 2011
Progress Update
Continue reviewing the 95% construction drawings for comments.
Met with the ITV group to review drop locations and changes in their equipment and or cabling.
Met with facilities application team on their requirements for cameras and emergency notifications.
G BE - 95% On Board Review with Design Team & Commission Team
Met with the ITV group to review drop locations and changes in their equipment and or cabling.
Met with facilities application team on their requirements for cameras and emergency notifications.
G BE - 95% On Board Review with Design Team & Commission Team
Tuesday, July 26, 2011
Progress Update
Continue reviewing the 95% construction drawings for comments.
Met with facilities and media resources to review all rooms with SIWS.
Scheduled review of construction drawings with the telephone team for August 9th.
Scheduled review of construction drawings with the ITV team for July 29th.
security and emergency notification requirements meeting scheduled for August 28th.
Review 95% construction drawings.
Met with facilities and media resources to review all rooms with SIWS.
Scheduled review of construction drawings with the telephone team for August 9th.
Scheduled review of construction drawings with the ITV team for July 29th.
security and emergency notification requirements meeting scheduled for August 28th.
Review 95% construction drawings.
Monday, July 11, 2011
Progress Update
Continue reviewing the 95% construction drawings for comments.
Continue reviewing the specification documents.
Scheduled drawing review with media resource.
Scheduled review of construction drawings with the telephone team for July 13th.
Scheduled review of construction drawings with the ITV team for July 13th.
Continue reviewing the specification documents.
Scheduled drawing review with media resource.
Scheduled review of construction drawings with the telephone team for July 13th.
Scheduled review of construction drawings with the ITV team for July 13th.
Thursday, June 23, 2011
Progress Update
Received the 95% construction drawings.
Reviewing the 95% construction drawings.
Setup meeting with other IT groups to review the construction drawings.
Setup a time to review the 95% CD for comments.
Prepare an FIP meeting to review the 95 % Construction Drawings.
Scheduled review of construction drawings with the FIP for June 29th.
Scheduled review of construction drawings with the NE team for June 29th.
Scheduled review of construction drawings with the Telephone team for June 29th. Scheduled review of construction drawings with the AV team for July 13th.
Scheduled review of construction drawings with the ITV team for July 13th.
Reviewing the 95% construction drawings.
Setup meeting with other IT groups to review the construction drawings.
Setup a time to review the 95% CD for comments.
Prepare an FIP meeting to review the 95 % Construction Drawings.
Scheduled review of construction drawings with the FIP for June 29th.
Scheduled review of construction drawings with the NE team for June 29th.
Scheduled review of construction drawings with the Telephone team for June 29th. Scheduled review of construction drawings with the AV team for July 13th.
Scheduled review of construction drawings with the ITV team for July 13th.
Tuesday, June 14, 2011
Progress Update
The 95% Construction Drawings are estimated to arrive this Friday (June 10th)
Setup an FIP meeting to review the 95 % Construction Drawings.
Setup an FIP meeting to review the 95 % Construction Drawings.
Friday, May 27, 2011
Project Activities
Updated communication log and reviewing the external duct bank.
There has been little activity on this project during past few months.
There has been little activity on this project during past few months.
Saturday, May 21, 2011
Progress Update
Updated communication log and reviewing the external duct bank.
The case work is for media resource and IT work area is being reviewed by the client.
Follow up with media resource review of the case work.
Follow up with facilities on ITV floor box design.
The case work is for media resource and IT work area is being reviewed by the client.
Follow up with media resource review of the case work.
Follow up with facilities on ITV floor box design.
Thursday, April 28, 2011
progress Update
Reviewing the media resource room and IT work space with client.
Reviewing the furniture design for both areas above.
Very little activity on the project
Updated communication log, Blog, and project portfolio.
Reviewing the furniture design for both areas above.
Very little activity on the project
Updated communication log, Blog, and project portfolio.
Thursday, April 14, 2011
Progress Update
Updated communication log, Blog, and project portfolio.
Bio -Revised sketch for terrace was completed by architects with less levels.
The bid may not go out until Fall of this year.
Bio -Revised sketch for terrace was completed by architects with less levels.
The bid may not go out until Fall of this year.
Wednesday, March 30, 2011
Progress Update
Updated communication log, Blog, and project portfolio.
Reviewing the project design with temporary GT academic campus manager.
Sent terrace design of outlets to ITV to review.
The ITV locations were sent back to facilities to hand off to the architects
The move list is still being worked on by facilities.
Reviewing the project design with temporary GT academic campus manager.
Sent terrace design of outlets to ITV to review.
The ITV locations were sent back to facilities to hand off to the architects
The move list is still being worked on by facilities.
Thursday, March 3, 2011
Ppogress Update
Updated communication log and reviewing the external duct bank.
The move list is still being worked on by facilities.
Work with the AV group to determine their change in AV equipment and impact to construction design.
Follow up on the client list from facilities.
Follow up with facilities on ITV floor box design.
Review ITV locations with ITV group.
Review the case work for the two IT areas.
ITV is working with the GT campus on additional location
The move list is still being worked on by facilities.
Work with the AV group to determine their change in AV equipment and impact to construction design.
Follow up on the client list from facilities.
Follow up with facilities on ITV floor box design.
Review ITV locations with ITV group.
Review the case work for the two IT areas.
ITV is working with the GT campus on additional location
Thursday, February 10, 2011
Progress Update
Met with facilities project managers to review CD 65% comments on Jan 7th.
Made some additional comments on the 65% construction drawings and forward them to facilities.
Updated communication log and reviewing the external duct bank.
Working with facilities to come up with an estimated list of people moving into BE.
Attended an AV demonstration on a new technology for the projector image.
Follow up on the client list from facilities.
Made some additional comments on the 65% construction drawings and forward them to facilities.
Updated communication log and reviewing the external duct bank.
Working with facilities to come up with an estimated list of people moving into BE.
Attended an AV demonstration on a new technology for the projector image.
Follow up on the client list from facilities.
Subscribe to:
Posts (Atom)