Updated communication log, Blog, and project portfolio.
Reviewing the project design with temporary GT academic campus manager.
Sent terrace design of outlets to ITV to review.
The ITV locations were sent back to facilities to hand off to the architects
The move list is still being worked on by facilities.
Wednesday, March 30, 2011
Thursday, March 3, 2011
Ppogress Update
Updated communication log and reviewing the external duct bank.
The move list is still being worked on by facilities.
Work with the AV group to determine their change in AV equipment and impact to construction design.
Follow up on the client list from facilities.
Follow up with facilities on ITV floor box design.
Review ITV locations with ITV group.
Review the case work for the two IT areas.
ITV is working with the GT campus on additional location
The move list is still being worked on by facilities.
Work with the AV group to determine their change in AV equipment and impact to construction design.
Follow up on the client list from facilities.
Follow up with facilities on ITV floor box design.
Review ITV locations with ITV group.
Review the case work for the two IT areas.
ITV is working with the GT campus on additional location