Friday, February 3, 2012

Progress Update

• As soon as the road work is completed the ground work for the building can start.
• New updated drawings have been completed.
• The FIP group as started reviewing the update construction drawings.
• Meetings have been scheduled with other IT groups to review the new drawings.
• ITV is planning to update their specifications for the building.

Next two weeks
• Monitor the road work for completion.
• ITV and facilities meeting is scheduled for Feb 15 to review the impact of their new specifications.
• Review the new construction drawings

Friday, January 13, 2012

Progress Update

As soon as the road work is completed the ground work for the building can start.
Forward new design of lower area to IT groups for any feedback that may impact the IT rooms.It does to appear the square footage for the IT rooms were impacted.
A meeting is scheduled for January 19 with ITV to review their new cabling request.