Friday, February 3, 2012

Progress Update

• As soon as the road work is completed the ground work for the building can start.
• New updated drawings have been completed.
• The FIP group as started reviewing the update construction drawings.
• Meetings have been scheduled with other IT groups to review the new drawings.
• ITV is planning to update their specifications for the building.

Next two weeks
• Monitor the road work for completion.
• ITV and facilities meeting is scheduled for Feb 15 to review the impact of their new specifications.
• Review the new construction drawings